Next Generation Hoardings

Next Generation Hoardings

  • Home
  • About
    • Open Hoarding System
    • Sustainability
    • Hoarding certification
  • Services
    • Shopping Centre Hoardings
    • Hoarding Component Hire
  • Contact
    • Request For Quote
    • General Enquiry
  • Tools
    • Hoarding Planner
    • Weight Block Calculator
    • Scope Creator
  • Knowledge Base

  • System basics
    • Panel vs Practical
    • Panels vs skins
  • Installation guide
    • Panel hoardings
      • Panel hoardings overview
      • Typical hoarding detail
      • Panel installation detail
      • Panel construction
      • Upright fixing
      • Corner braces
      • Returns
    • Doors and openings
      • Hanging doors
    • Installation details
      • Hoardings without returns
    • Practical hoardings
      • Practical hoardings overview
      • Typical practical hoarding detail
      • Upright fixing
      • Doorways
      • Doorway frame
      • Skin fixing specification
      • Returns
      • Splays
    • Uprights and load ratings
      • Upright drawings and load ratings
      • Upright overview
      • Welding and material specification
      • Fabrication setouts
      • Load ratings and weight blocks
      • Offset uprights
      • Counterweights
  • Project guides
    • Planning and installation
      • Retail hoarding installation
    • System interfaces
      • Temporary fencing integration
Installation Guide
Next Generation Hoardings Next Generation Hoardings
Installation Guide
Panel Hoardings Practical Hoardings (skins) Uprights & Load Ratings

Hoarding Installation: Panels vs Skins

Skins are practical hoardings: sheet materials fixed to timber studs on site. Here is how installation differs from prefabricated panels.

  1. Home
  2. Hoarding Installation: Panels vs Skins
02

Two ways to assemble the hoarding

In this guide, skin hoarding means practical hoarding. Sheets of MDF or plywood form the face of the wall and are fixed to timber studs at the installation location. The NXGN manuals call this method practical hoarding and refer to the sheets as skins (SK).

Panel hoarding also uses a sheet skin, but the skin is attached to a timber frame to make a complete panel before installation. Those panels are then brought to site and joined along the hoarding line. The difference is how the wall is assembled, rather than a choice between two face materials.

Both methods use NXGN steel uprights and weight blocks. Their construction and fixing details differ, so start with the manual for the method you intend to build.

03

Panel hoarding: prepare panels, then install them

Start with the layout: the length and height of each run, door positions, returns and changes of direction. These determine the panels, door heads and corner details to prepare. A return takes the hoarding back towards the shopfront or work area; a splay forms an angled change in direction.

Fabrication brings the timber frame and sheet skin together before the site installation. Plan how the finished panels will be transported, unloaded and moved through doors or lifts, including the room needed to turn and position them.

On site, the prepared panels are joined and connected to their uprights using the panel installation details. Door heads, returns and splays have their own connections. Prefabrication moves work out of the site installation window, while panel handling, connections and finishing still need time.

Read the panel hoarding manual → Panel installation drawing →
04

Practical hoarding: assemble framing and skins on site

For practical hoarding, timber, sheet skins, uprights and weight blocks are delivered as separate components. Set out the same layout information before assembly, including openings and changes of direction. Allow space for storing materials, cutting timber and sheets, and working along the hoarding line.

The practical-hoarding details show how upright studs connect to the steel uprights and how skins are fixed to the studs. Door openings use doorway framing and door-head skins. Returns and splays need the additional studs and upright arrangements shown in their respective details.

This method shifts frame and skin assembly into the site programme. It can suit a project where fabricating complete panels in advance is impractical, provided there is enough working space and time on site. Check the delivery route for full sheets and timber as well as the supporting hardware.

Read the practical hoarding manual → Skin fixing specification →

Different connections, different drawings

Panel installation drawing showing adjoining framed panels and their upright connections

Panel hoarding: the installation drawing shows how completed panels connect to each other and to the uprights.

Practical hoarding drawing showing sheet skins fixed to timber upright studs

Practical hoarding: the skin fixing drawing shows the connection between the sheets and timber studs.

Plan the work around the installation method

Stage Panel hoarding Skin / practical hoarding
Before delivery Coordinate panel sizes, openings and corner details for fabrication. Arrange transport and handling for assembled panels. Coordinate the layout and material quantities. Arrange a work area for cutting and assembly on site.
During installation Position and connect prepared panels, with the supports and opening details shown in the panel manual. Assemble the upright studs, framing and skins, including the details around doors, returns and splays.
Finishing Allow for panel joints, screw positions, edge treatment and the selected face finish. Allow for sheet joints, screw positions, edge treatment and the selected face finish.
Removal and storage Plan handling and storage for any panels being retained, including protection of faces and edges. Plan dismantling and sorting of sheets, timber and hardware, with space to inspect and store reusable components.
07

Finish, reuse and total project effort

A consistent finished face depends on the framing, sheet alignment, joints and finishing work. Panels let you prepare more of that work before delivery. Practical hoarding brings more of it onto site. Allow time for the chosen paint, graphics or other face treatment in either programme.

Think about the next use when planning removal. Retaining complete panels needs suitable handling and storage; retaining practical-hoarding materials means separating and sorting the components. Reuse depends on their condition after dismantling and whether they suit the next layout.

Compare fabrication, delivery, site labour, finishing, removal and storage together. A shorter assembly window does not by itself establish the lowest total cost, and compact material storage does not remove the need for a suitable work area.

08

Include the supports and openings in the plan

The visible wall is only part of the installation. Include the space behind it for uprights and weight blocks, together with door operation, returns and corner connections. Record the hoarding height and geometry alongside the chosen construction method.

Use the matching construction manual with the upright and load-rating drawings to work through the support arrangement. The manuals provide the member sizes, fixing specifications and details needed for the individual connections.

Uprights and load-rating drawings →

Take the method into your project plan

Use the comparison for an overview of the trade-offs, then record the layout and project requirements. Keep the matching installation manual alongside the plan.

  • Compare panel and practical hoardings
    Review delivery, access, working space and preparation side by side.
  • Open the hoarding planner
    Develop the layout, including runs, openings and changes of direction.
  • Browse the installation guide
    Read the manuals or find a specific construction detail in the article index.
  • Request a project quote
    Share the proposed layout, method, timing and site access information.
Next Generation Hoardings Logo

Open hardware. Connected workflow.

NXGN's open retail hoarding system lets contractors and owners fabricate their own hoardings, mark up plans, calculate materials and job prices, and install hoardings without proprietary lock-in. Our platform keeps customer details, plans, quotes and installation records together, so you can organise each job from enquiry to completion.

Open System

Installation Guide Panel vs Practical Load Ratings Counterweights

Platform

Hoarding Planner Scope Creator Weight Calculator

Work With NXGN

Shopping Centres Component Hire About NXGN Contact
Contact Us Today hoardings@nxgn.au
0477123901 Contact Us Today
© 2026 Next Generation Hoardings Pty Ltd.
Built by Vortex